We have received an update from the Council regarding the planned refurbishment of the outdoor track. The planned work is to start on site in the last week of February/first week of March.

All works to remove the existing surface and relocate the field event areas will be completed by the end of March/first week in April. Then they will need to wait until favourable weather in May to complete the new surfacing works. There is no slack in the programme as the contractors will not risk putting down the new surface in April as it is weather dependent.

As a result, the club will have to reschedule all outdoor training from the start of March until the end of May.